Inline Scrubber for a Carbon Capture and Storage (CSS) Project

In November 2025, Midsund Industriservice was awarded a contract for the express delivery of an inline scrubber equipped with welded high-tech process internals for a CCS project in Norway.

The vessel was fully fabricated at our workshop in Midsund, including all welding activities and the installation of internal components. All materials were procured from qualified and well-established suppliers to ensure compliance with project requirements and the demanding delivery schedule.

To meet the exceptionally short lead time, dedicated welders and fitters worked extended shifts, including weekends, enabling the successful completion and delivery of the vessel in accordance with the project timeline.

Image6
IMG 2614
IMG 2615

Four Subsea Pressure Vessels for Geological Research Applications

These pressure vessels were manufactured at the company’s workshop in Midsund. The project integrated a wide range of engineering disciplines, including design for multiple load cases such as hydrogen-induced stress cracking (HISC), dynamic impact loads, and fatigue. Advanced materials were utilized throughout, including 15-5 PH stainless steel, 1.7225 alloy steel, 22Cr duplex stainless steel, and 25Cr super duplex stainless steel. The scope also included welding of dissimilar materials, high-precision post-weld machining, and execution of complex factory acceptance testing (FAT).

IMG 6950

The engineering phase extended over approximately three years to ensure compliance with all applicable load cases and full conformity with EN 13445 and the Pressure Equipment Directive (PED) 68/2014/EU. Structural integrity and load verification were performed using finite element analysis (FEA) for all components. 

One of the key fabrication challenges was managing welding-induced deformations resulting from heat input. To mitigate irreversible distortions that could not be corrected by post-weld machining, all welding activities were carried out in accordance with carefully planned and controlled welding sequences.

The first pressure vessel was delivered and successfully tested in December 2025. 

 

Image20

Two Dehydrators and a Separator for Confidential Project

All pressure vessels were designed in accordance with EN 13445 and supplied with CE marking in compliance with the Pressure Equipment Directive (PED) 2014/68/EU. The material of construction was 25Cr duplex stainless steel qualified in accordance with NORSOK M-650. Stringent requirements in accordance with API RP 528 were applied for this delivery.

The main shell longitudinal and circumferential seams were welded using the submerged arc welding (SAW, process 121) method. All vessels were equipped with complex process internals, as well as integrated platforms and ladders to meet operational and maintenance requirements.

IMG 20250711 095050
Bilde5
Image10

Pressure Vessels for Sand Treatment on Hugin platform

We delivered three pressure vessels which are designed in accordance with EN 13445 and carry CE marking in compliance with PED 2014/68/EU. The material of construction is 22Cr duplex stainless steel, qualified in accordance with NORSOK M-650.

Each vessel is equipped with complex process internals to meet operational requirements. All primary weld seams are executed using the Submerged Arc Welding (SAW) process (ISO 4063: 121) to ensure efficiency and excellent weld quality.

D 44 CE006 B 5

Replacement of a Section of a MEG Flash Separator at an Onshore Gas Processing Plant

This project involved everyone from our team. It started with detailed design and engineering and thorough planning in order to minimize on-site work. After thorough evaluation of all possibilities, replacement of complete vessel shell strake was selected as the most suitable solution. Shell strake was prefabricated at our workshop in Midsund. It was cladded in with Alloy 625 weld overlay and with installed 2 off tangential nozzles from solid Alloy 625.

After completion of hot work Midsund Industriservice performed NDE of all welds, on-site pressure test and surface treatment. Pressure vessel was sandblasted and painted before subsequent insulation.

This job also included installation of a new vortex breaker and replacement of a connecting flange. 

IMG 20230529 170719
IMG 20230529 025707

Pressure vessels for Produced Water Treatment(PWT) on a FPSO

Scope of supply for this major project consist of 7 off pressure vessels for Rosebank PWT Package. 

All vessels are designed according to EN13445 with UKCA certificate performed by DNV. Material of construction is 22Cr duplex according to Norsok M650. All main seams well welded by SAW (121) method.

All vessels are equipped with complex process internals.

Image17
Rosebank 3d model 2

Pressure vessels for offshore wind HVDC platforms

Midsund Industriservice was awarded sevaral packages consisting off expansion pressure vessels (ER246) for Norfolk Vanguard East & West and East Anglia 3 offshore wind HVDC platforms.

Expansion tanks are designed according to EN13445 with both CE and UKCA certificate. Material of construction is 316/316L.

External surface treatment is according to Norsok System 6C (insulated surface) and Norsok System 6A (exposed surface) 

Image18
Bilde3

Storage tanks for offshore wind HVDC platforms

Midsund Industriservice was awarded sevaral packages consisting of 18 off rectangular storage tanks – 4 off Diesel Storage Tanks, 2 off Fresh Water Tanks and 12 off Seal Pots. All tanks are part of Norfolk Vanguard East and West offshore wind HVDC platforms. 

For East Anglia 3 offshore wind HVDC platform we had a similar scope that consist of 9 off rectangular storage tanks – 2 off Diesel Storage Tanks, 1 off Fresh Water Tank and 6 off Seal Pots. 

Diesel Tanks and Fresh Water Tank are large rectangular single wall storage tanks. Tanks were designed by FEA with fabrication details according to API 650. Tanks are insulated and equipped with heaters and with platforms and ladders for access. Material of construction of Diesel Tanks is 316/316L, Fresh Water tank is made of 22Cr duplex (inner shell) with stiffeners from 316L. 

Seal Pots are relatively small rectangular tanks made of 25Cr Super Duplex. 

External surface treatment is according to Norsok System 6C (insulated surface) and Norsok System 6A (exposed surface).

2023 07 12 07 59 47
Pots 1
Bilde4

Atmospheric tanks for CCS project

Midsund Industriservice was awarded a PO for complete delivery of 7 off atmospheric tanks for Norcem CCS – this project was a part of Longship CCS, the pilot Carbon Capture and Storage project in Norway. 

These atmospheric tanks, which was constructed in 316L and P355 NH/NL2, are used as storage tanks for different liquids used in carbon capture process. Tanks are delivered with insulation (heat conservation), heat tracing and electrical heaters, where applicable.