Replacement of a Section of a MEG Flash Separator at an Onshore Gas Processing Plant

Image14

This project involved everyone from our team. It started with detailed design and engineering and thorough planning in order to minimize on-site work. After thorough evaluation of all possibilities, replacement of complete vessel shell strake was selected as the most suitable solution. Shell strake was prefabricated at our workshop in Midsund. It was cladded in with Alloy 625 weld overlay and with installed 2 off tangential nozzles from solid Alloy 625.

 

After completion of hot work Midsund Industriservice performed NDE of all welds, on-site pressure test and surface treatment. Pressure vessel was sandblasted and painted before subsequent insulation.

This job also included installation of a new vortex breaker and replacement of a connecting flange. 

Image16